Nscale filed an amended IPO prospectus on November 12. It plans to list on the New York Stock Exchange as NSCL, with Goldman Sachs, J.P. Morgan and Morgan Stanley leading the deal, and it still hasn't set a price range. Bloomberg has reported Nscale is seeking a valuation of about $30 billion, with some investors pushing back toward $16 billion to $19 billion. The new filing shows $307.5 million of revenue and a $1.69 billion net loss for the nine months to September 30, against about $103 billion of contracted value.
The prospectus tells you what Nscale has sold. Its staff records show who is building it and how fast. Nscale's workforce more than tripled between January and October, mostly engineers, and it has hired more people from Oracle than from Microsoft and AWS combined. Then, in October, engineering hiring fell to less than a fifth of its monthly pace over the summer. The same months, several of the company's earliest senior people left.
Key points
- Oracle comes first. Nscale has hired nearly three times as many people from Oracle as from Microsoft, and more than from Microsoft and AWS combined. Future-tech, Liberty Global, Vantage Data Centers, Amazon and Meta follow.
- Engineering hiring slowed sharply in October. Engineering hiring climbed from March, peaked in May and June, then slowed significantly in October, to less than a fifth of its summer pace.
- The early bench is leaving. The President of Data Centres, who was Nscale's first COO, left in August. An SVP, a board member, the FP&A director and the head of procure-to-pay left in August and September.
- New people at the top. Nscale lost C-level staff in August and September and added new ones in October and November, weeks before the listing.
- Microsoft passed on Texas. Microsoft declined an option to more than double its Texas capacity with Nscale, a decision a Reuters source says was made months before the IPO filing.
Where Nscale hires from
Nscale spun out of the crypto miner Arkon Energy in 2024. In two years it has hired from the companies it now competes with for customers. Oracle comes first, followed by Microsoft, AWS, Future-tech, a data center build contractor, Liberty Global, Vantage Data Centers, Amazon and Meta.
Oracle's people matter here for a specific reason. Oracle has spent 2026 cutting one version of itself to fund a data center business (my Oracle layoffs page has the rounds). And Nscale keeps hiring Oracle's cloud and data center people.
The people leaving Nscale are going to Google, Salesforce, Cohere, Panattoni Data Centres, Fractile and Core42, G42's cloud unit in Abu Dhabi. The Abu Dhabi Investment Council is also in Nscale's pre-IPO money. The Council is part of Mubadala (who runs Mubadala and where its money goes).
| Where Nscale hires from | Where Nscale's people go |
|---|---|
| Oracle | |
| Microsoft | Salesforce |
| Amazon Web Services | Core42 (G42, Abu Dhabi) |
| Future-tech | Cohere |
| Liberty Global | Panattoni Data Centres |
| Vantage Data Centers | Fractile |
Nscale IPO: quick answers
When is the Nscale IPO?
Nscale has not set a date or price range. Bloomberg has reported it is seeking a valuation of about $30 billion. It filed for a NYSE listing under the ticker NSCL on September 18, 2026, and filed an amended registration statement on November 12.
Who invested in Nscale before the IPO?
Nscale raised $3.36 billion in convertible notes led by Third Point, with Nvidia, Apollo, Citadel, Hudson Bay Capital, the Abu Dhabi Investment Council and 8090 Industries. Nvidia's $1 billion tranche was due by mid-November. The notes convert into shares when Nscale lists.
Did Microsoft cancel its Nscale contract?
No. Microsoft declined an option to more than double its capacity at Nscale's Texas site. The existing Texas contract remains in place.
Is Nscale still hiring?
Nscale's workforce grew more than threefold in 2026, but engineering hiring slowed significantly in October.